@janl@narrativ.es @polotek@social.polotek.net when I’m working with teams that have little experience in estimation I ask them to work very strictly on one-week sprints due to point #4 you make. If a team can’t estimate what they can get done in a week, there’s no way they can estimate months at a time. By enforcing a short interval they have the chance to start learning how to estimate with smaller item sizes first— after which they can start increasing their skill.