Most boards show where tickets are, not what's happening with the work.
A ticket that's been stuck in "In Progress" for three days looks identical to one that's actively being worked on. And as long as that's the case, you're managing activity, not understanding flow.
What does flow mean anyways? That's what this interactive page is for:
https://no-bullshit-agile.de/wip/
#kanban #agile #flow
Replies (3)
-
@RosannaSibora@fosstodon.org 2026-03-22 16:10
@nobsagile@mastodon.social very good point! This is why at @openproject@fosstodon.org we are planning to show dependencies between work packages on the boards but also if a card is blocked. #roadmap
-
@AAMfP@fosstodon.org 2026-03-22 20:32
@nobsagile@mastodon.social Nice one!
-
@Unsinn@berlin.social 2026-03-23 20:52
@nobsagile@mastodon.social that's a really cool article about the concept of flow and WIP. Thank you for sharing this.