'The opening of England’s first new reservoir in more than three decades has been delayed by five years while its cost has more than doubled …
'Thames Water is also planning a privately financed reservoir in Abingdon, Oxfordshire, where the estimated cost has tripled …
'Although the amount of rain in Britain has increased by 10 per cent since the 1970s, a lack of storage means that it cannot be retained …
'Ofwat is planning nine other new reservoirs, as well as eight water recycling schemes, two desalination plants and nine transfer schemes that will bring water from wetter areas in the north to the drier south.
'… construction at Havant Thicket had encountered unexpected geological conditions requiring parts of the reservoir to be redesigned.
'… also due to the expanded size of the scheme, which includes a fivefold increase in capacity and a controversial water transfer and recycling project that is yet to get planning approval'.