17gw of heat is both under and over estimate. 3,600 of those industrial-scale generators to power Stratos Caterpillar 2.5mw generators have maximum efficiency of 45%, and so 19gw is peak thermal power. that is roughly 26 hiroshimas per day. It’s an over estimate because datacenter cpu/gpu capacity utilization is on average under 10%. It could still produce all that power for export to trap all that heat in a valley.