@edza We have a contractor we’ve used several times for small to medium sized jobs on our house (he also does major renos). On our jobs, “It’ll be 7 or 8 days” was 7.5 days. “Expect it to take 6 weeks” was 6 full weeks + 2 mornings in the 7th week. I’ve noticed that he plans it all out ahead of time (including using CAD s/w), has subcontractors who know he’ll drop them if they’re unreliable, builds in a reasonable amount of buffer and doesn’t allow feature creep. He’s like a god to me.